• Location

    Corner of Batman Avenue & Olympic Blvd, Melbourne

  • Completed

    May 2013

  • Architect

    Croxon Ramsay & Peddle Thorp Interior Design (PTID)

  • Area

    7,000sqm

  • Type

    Fitout

  • Duration

    12 months

  • Project Manager

    Coffey Projects

Delivering a range of sporting facilities

Located at the heart of Melbourne's Olympic Park sporting precinct, the venue now features upgraded sporting, retail, and administration facilities within the Westpac Centre.

Schiavello Construction VIC delivered the interior construction and facilities upgrade of the 7,000sqm space, including an altitude training room, players lounge, sports medicine facility, gym, Spotted Gum baseball court, management spaces, and a mezzanine floor with altitude training rooms and gym area.

Schiavello also constructed new communal shower blocks, change rooms, coach areas, amenities, completed lift works and more.

Ensuring operations were not disrupted

Ensuring the sporting facility remained operational throughout the entire project was paramount to the football department. Temporary training and staff areas were set up during construction, and new hot and cold hydrotherapy pools were set up as an alternative to the club’s existing facilities that were upgraded during the course of the works.

collingwood football club melbourne timber joinery lobby entry
collingwood football club melbourne mezzanine gym trusses

Constructing a new mezzanine

The construction of the sporting facility’s new mezzanine level posed a challenge due to latent ground conditions. The facility had previously housed a swimming pool built for the 1956 Summer Olympics and subsequently covered by a basketball court. The ground conditions beneath were unknown and inaccessible until well into the project - posing a significant risk to the construction programme for the mezzanine structure.  Schiavello Construction VIC helped the team overcome this challenge by undertaking preliminary testing and by being quick to implement design changes resulting from the necessary re-engineering efforts.

Innovative solutions to logistical challenges

An additional challenge to the works was the limited access to the main gym area, due to the narrow door and passageway adjacent to the main lap pool.  Due to the nature of the structural works required for the mezzanine, our construction team needed to construct a temporary bridge over the pool to allow access to the necessary plant, equipment and materials.

Schiavello Group's holistic offerings

With local manufacturing capabilities and integrated furniture solutions, Schiavello offered a holistic service including the seamless manufacturing of joinery elements by Prima Architectural Joinery, as well as workplace furniture to support 52 administrative offices by Schiavello Systems.

Schiavello’s Centric workstations with System 45 panels met the designers' functional and aesthetic requirements. Custom storage units, pedestals and Humanscale M2 monitor arms complimented the range.

Constructed in 12 months

The project was completed within a tight 12-month construction programme made possible by a high level of collaboration between Schiavello and all parties involved, including design firms Croxon Ramsay and Peddle Thorp Interior Design, and project manager Coffey Projects. This enabled us to support and work around an array of moving parts that kept the sporting facility alive during the football season and beyond.